Track Record

Proven in the field.

120+ wells delivered across 18 countries. Browse the engineering galleries below.

1 / 3

DP-3 drillship on station over the Atlas-1 wellsite.

Gulf of Mexico

Atlas-1 Deepwater Exploration Campaign

Water depth
2,850 m
Total depth
9,650 m MD
Rig type
DP-3 drillship, dual derrick
Scope
HPHT exploration well, MPD system

Delivered 11 days ahead of AFE with zero recordable incidents. First MPD deployment in the block de-risked a narrow pore-pressure window.

1 / 3

Jack-up rig on location, legs extended to seabed.

North Sea

Corsair Jack-up Batch Drilling Program

Wells
14-well development batch
Rig type
Harsh-environment jack-up
Duration
26 months continuous ops
Scope
Top-hole batch set, completions, tie-in

Batch methodology cut average well time 22% versus sequential drilling; 96.4% operational uptime across the campaign.

1 / 3

Work-class ROV performing tree cap seating checks.

West Africa

Meridian Subsea Tieback & Tree Installation

Trees installed
6 vertical subsea trees
Water depth
1,420 m
Scope
Tree install, jumper metrology, IRM
Support
Two work-class ROV spreads

All six trees landed and tested within one weather season. ROV inspection campaign closed 100% of class findings.